Engineering: the CDR 2026 design review

On 2026-10-27 the project finished a design review against the NASA NPR 7123.1D Critical Design Review criteria, tailored for a Class D CubeSat. This page shows what it found, what it decided, and what it left for hardware and for the principal investigator (PI). Report: SQSO-REV-CDR-002 version B

What the review is, and is not

In the report's own words (§1.2):

Verdict and maturity

No review action is open. Every one of the 412 findings carries a final disposition. "Closed" means the evidence is recorded in the repository; where only hardware or an outside party can supply it, the finding is closed as a dated verification item or decision point, not as a result. SQSO-REV-CDR-002 §7.1

The report's maturity statement (§7.2):

Judged honestly against Table G-7, SMART-QSO is at the level of a strong PDR with CDR-depth analysis, not past a CDR:

What it gives the independent PDR is a design with no known open defect, the evidence for every claim, and the list of what only hardware can show.

Review item discrepancies (RIDs)

412 RIDs were raised: 32 of severity 1 (mission or safety critical), 211 of severity 2 (must close before fabrication), 169 of severity 3 (should fix). Rounds 3 and 4 (independent closure verification) reopened 45 RIDs and raised 106 new findings; 45 of the reopened and 102 of the new are since closed and 4 were dispositioned when raised. Open implementation RIDs: none. SQSO-REV-CDR-002 §6

RID dispositions when raised (round 1) and final (CDR report §6)
DispositionRound 1Final
Closed by analysis2531
Closed by design change101279
Closed by chair decision4235
Verification item4633
Decision point (dated)1534
Implementation1830
Total412412

Margins at the review

Every margin is a prediction from analysis or simulation; none is measured. The mission simulation (version G) ran the unchanged flight software through 730 days of operations and found 0 anomalies and 0 warnings in 50 checks; a beacon was decoded on 95.9 % of 28,567 simulated passes, and the generated beacon text cost 0.065 Wh per accepted line under assumed inputs. Mission simulation §7

Margins at the review (CDR report §3.3)
QuantityRequirementPredictedMarginSource
Mass≤ 2.00 kg (design), 2.5 kg NovaMEV 1.755 kg, CBE 1.520 kg (ballast, harness 85.6 g with the real splices and tabs, cell retention)+14.0 % (+42.5 % to the Nova)MASS_BUDGET 3.3
CG, stowed±20 mm(+0.1, −0.3, −1.4) mm CBE (CAD)> 18 mmMECHANICAL_DESIGN B
Deployed inertiaIyy ≥ 1.03 × max, axis within 5° of +Y1.056 / 1.047 (CBE / MEV, four AntS elements, C-13 ballast, harness), 0.9° / 1.0°; MEV 5th percentile 1.036 at 2 mm placement scatterMetMECHANICAL_DESIGN B §5
First mode, stowed> 40 Hz170 Hz CBE / 162 Hz MEV (FE, 2.0 mm EPS, rod on the −X wall)× 4.0–4.3STRUCTURAL_ANALYSIS
StrengthMS ≥ 0 (NASA-STD-5001B protoflight factors at MPE + 3 dB)Lowest +0.97 (+0.86 at MEV masses)PositiveSTRUCTURAL_ANALYSIS
PCB fatigue (Steinberg)MS ≥ 0+0.42 to +0.72 at CBE, +0.14 to +0.51 at MEV (2.0 mm EPS and carrier)PositiveSTRUCTURAL_ANALYSIS
Wing deployment torqueNASA-STD-5017B torque margin ≥ 0 at end of travel, at −55 °C+0.08 (one spring out +0.07); release-energy ratio 1.90 with the 10 s burn (C-17)Positive; resistive torque below −40 °C verified at −55 °C (VI-MECH-01..03)MECHANISMS_ANALYSIS E
Power, EOL, sun-pointed≥ 20 %3.84 W delivered with the photodiode-and-albedo pointing of C-23 (3.79 W in the worst trial; 3.92 W with +Y held on the Sun) against the bottom-up ACTIVE load 2.60 W with the heater and the transponder+45 % (+43 % worst trial), PBA method; +70 % on the 2.26 W allocation by the BASELINE methodPOWER_BUDGET_ANALYSIS 2.5 §4; ADCS_DESIGN 1.9 §11.6; BASELINE §5
Power, EOL, tumbling≥ 20 %2.48 W against the bottom-up ACTIVE load 1.91 W with the heater and the transponder+27 %, PBA method; +33 % on the 1.86 W allocation by the BASELINE methodPOWER_BUDGET_ANALYSIS 2.5 §4; BASELINE §5
Depth of discharge≤ 10 % per eclipse≤ 3.5 % as flown (SIL G, 475 km); 2.8 % worst contingency (PBA 2.2)× 2.9SIL_MISSION_SIMULATION G §7; POWER_BUDGET_ANALYSIS
Battery temperature0 to +45 °C charging≥ +4.4 °C at 14.0 V; +3.6 °C at the 12.0 V floor (0.70 W heater); +1.3 °C with a 0.10 W/K mount at 14.0 V; −1.5 °C with the wings stowed at 0.70 W (charging then inhibited in hardware)Met in operation; stowed-wing case THM-03THERMAL_ANALYSIS 2.6
Beacon link, 5°≥ 6 dB (median gain)+7.9 dB+1.9 dBLINK_BUDGET 3.2
Telecommand link, 10°6 dB with interference allowance≥ +8.4 dB at both variants' minimums (variant A +9.5 dB), receiver as designed, 10th-percentile gain, pointing included (≥ +6.6 dB at 5°)≥ +2.4 dBLINK_BUDGET 3.5 (C-14)
Sun pointing (C-23)Pointing loss ≤ 5 % of sunlit generation and the Sun within 30° of +Y ≥ 95 % of sunlit time, every trial2.0 % (3.2 % worst trial) and 100 % with the face photodiodes and Earth albedo; 5.0 % / 96.3 % worst at the 7 mA·m² residual-dipole limit (C-24); one wing at preset 0 ≤ 2.0 %MetADCS_DESIGN 1.9 §11.6
Detumble and capture≤ 3 orbits≤ 1.8 h, the slowest in-specification trial (tip-off σ 10°/s, up to 30°/s; ≤ 1.2 orbits)× 2.5ADCS_DESIGN 1.9 §11.4
AI beacon energy (D5, C-20)≤ 0.1 Wh per accepted beacon line0.065 Wh (SIL G mean under assumed inputs; 0.090 Wh at a 30 % filter reject rate)× 1.5SIL_MISSION_SIMULATION G §7; go/no-go VI-02 on the EM
Total dose, 2 mm Aldesign 10 krad, margin ≥ 24.69 krad at 475 km, 4.91 at the 485 km cap× 2.13 (× 2.04 at the cap); ≥ 2.1 mm kept (× 2.17 at the cap)RADIATION_ANALYSIS F
Orbital lifetime≤ 5 yr after mission, P ≥ 0.9P ≥ 0.997 at 475–485 km (planned-end reading); wings-failed probability 0.29 %Met; fallback 460 kmODAR Draft D
Casualty risk≤ 1:10,000No fragment > 15 J (nominal); 1:47,000 worst sensitivityMetODAR Draft D
Reliability(goals 0.95 / 0.80 / 0.60)0.75 / 0.61 / 0.51 (L1 / L2 / L3); 0.86 / 0.71 / 0.59 with the burn-in and flatsat programmePI acceptance (REL-01)RELIABILITY 2.1
Schedule float≥ 9.6 weeks (67 d, GOLD 1.06) to the integrator milestone for 2028-11+71 days (10.1 weeks; layout re-estimated, reliability programme and the board firmware tasks included; −20 d with one layout designer)Met by 0.5 weeksSCHEDULE Rev E; schedule_cpm.py

Chair decisions: proposals awaiting the PI

The review chair made 24 decisions (C-1 to C-24). They are proposals by AI reviewers, not decisions of a board, and bind nothing until the PI ratifies or rejects them (action DA-01, due 2027-01-12). SQSO-REV-CDR-002 §7.1 SQSO-SCH-001 §5

The 24 chair decisions (CDR report §4)
Chair decisions, pending PI ratification (CDR report §4)
#DecisionRIDs
C-1Planning launch the last Transporter of 2028 (about 2028-11); June 2028 an opportunityPM-05, LV-10
C-2Deployment altitude 475 km target, 465–485 km band, 485 km cap; 460 km if the FCC counts an early failure as the end of the missionODA-01, ODA-05
C-3Layout B; AntS 2 m elements along ±X; CR0002 rods; deployed-inertia requirementSTR-01, STR-02, RF-03
C-4Spin 8°/s, nutation damping 3·10⁻⁴ (1·10⁻⁴ without gyro); the round-3 gain sweep (ADCS_DESIGN 1.9 §11.4) keeps it on the Iyy/Izz 1.005–1.05 results, and the protection against a degenerate plant is the Iyy ≥ 1.03 × max mass-properties limit, not the gainsGNC-02, P3F-G-04
C-5Two resistors per wing on their own 0.8 A drivers, 8 s burns, wings before antennasSMA-05, EPS-18, REL-03, STR-15, STR-16
C-6Three deployment switches DS1–DS3 on three railsLV-05, SMA-01, EPS-04, RF-14
C-7Integration SOC 60 % ± 5 %, separation ≥ 40 %, drain ≤ 20 µALV-06, SMA-10, EPS-20
C-8Telecommand stations ≥ 1,000 km apart, each able to command alone; agreements by 2027-01-05LV-08, GND-01
C-9Reliability 0.75 / 0.61 / 0.51 (0.86 / 0.71 / 0.59 with the ≥ 500 h flatsat and ≥ 200 h FM burn-in programme) proposed for acceptance as Class D risk; the acceptance itself is the PI's (DA-02, 2026-12-15)REL-01
C-10transponder.rs and ops_state.rs added to the safety-critical listFSW-05
C-11Heater set points +5/+9 °C; ≈ 207 Ω heaterTHM-02, BUILD_VS_BUY §4.5
C-12Two centre supports on the EPS, OBC and carrier boardsSTR-05, MECHANICAL_DESIGN
C-132 × 10 g non-ferromagnetic ballast on the Z axis at the end frames, so the deployed inertia ratio keeps margin with all four AntS elementsMCAD-09, RFB-11
C-14Telecommand stations radiate ≥ 64 dBm EIRP above 10° elevation: ≥ 100 W PEP into ≥ 15.5 dBic outside the 47 CFR 2.106 US270 areas (variant A), ≤ 50 W PEP at the transmitter output into a ≥ 17.8 dBic stacked pair inside them (variant B); commands only above 10°RF-23
C-15Harness wire under the EPS tied to the deck straps and shear panels; only connector strain-relief ties on the EPS board (EPS Steinberg +0.23, −0.52 otherwise)MCAD-11
C-16Battery-lead shorts: the two positive-leg fuses are diverse by design (F0A MIL-PRF-23419/12 from AEM, F0B MIL-PRF-23419/8 from Littelfuse), with F0N in the negative leg the third, so BSA H3b is 2-fault tolerant without counting two same-part fuses as independent (an earlier wording did; revised after the board FMEA). NRCSD safety-engineer concurrence for the ISS backup pathEPSB-10, P3E-02
C-17Burn 10 s per resistor (was 8 s): at the bounding −55 °C the 8 s burn gives a release-energy ratio of only 1.52 against 1.5; 10 s gives 1.90 inside the 12 s hardware one-shotP3S-01
C-18The AntS deploys only when its own reported temperature is ≥ −17 °C (the −20 °C qualified minimum plus 3 °C sensor tolerance), deferring to the next 50-min slot without spending an attempt; after 30 deferrals (about 25 h, which covers the wings-stowed case where it never warms) it releases after 20 min of continuous sun, and after 3 unreadable temperatures it follows the thermal analysis's schedule (the first 20 min of sun from S + 69 min); on ground command it deploys at once. An ungated release after an eclipse separation would be at −44 °C; the gate opens within 177 min in every nominal case, before the first commanding pass (median 6.4 h). The wings still go first at S + 30 minP3T-09
C-19The transmitters stay silent while the AntS deployment is pending (deferred by C-18, or not yet attempted); the downlink starts when the AntS reports deployed or its sequence ends, never before the 45-min RF silence. Keying into stowed elements trips the VSWR protection (SIL-37: two 10-min stops, 1,312 s beacon gap) and stresses the PA, and nothing is lost: the first commanding pass (median 6.4 h) is later than the gate's nominal worst case (177 min); a failed AntS sequence still gets its stowed-antenna beacon. Off the nominal path (a plausible but cold reading held for the whole cap, e.g. a wrong temperature conversion before AV-V7 confirms it) the spacecraft is silent for up to about 25.8 h; the cover is the blind forced DEPLOY_RETRY in the commissioning planSIL-37 (P3T-09)
C-20One Smart Beacon burst definition, the one the design implements: a Jetson power-on of at most 10 min and at most 3.6 kJ at the carrier input, ended early by the energy gate. The go/no-go metric is energy per accepted beacon line ≤ 0.1 Wh (360 J), counted on accepted lines (not per burst), measured on the EM over ≥ 30 bursts (VI-02) and confirmed in commissioning over ≥ 10 bursts (MSC E-02). SYS-512, VI-02 and the D5 960 J figure are revised to match (CR)P3F-G-03
C-21With one wing deployed and the ground unable to say which, the spacecraft uses preset 0 (both wings) rather than guess between presets 1 and 2: the wrong one-wing preset is the case not analysed, preset 0 costs 2–3 % of power. Presets 1 and 2 are used only after the commissioning identification procedure (array current against the sun-sensor angle over a spin) names the wingP3F-G-06
C-22The attitude-knowledge requirement is restated as what the control law uses: sun-vector knowledge within ±5° in sunlight from the sun sensors, and rate knowledge from the gyros. A spin-stabilised sun-pointer needs no onboard three-axis estimator, so the EKF/TRIAD of ADCS_DESIGN §4.3 is removed from the flight baseline; the Monte Carlo measures the sun-vector error to verify itP3F-G-07
C-23With the face photodiodes and Earth albedo modelled (ADCS_DESIGN 1.9 §11.6) the spin-stabilised sun-pointer holds 12° mean and 74 % of sunlit time within 15°, and its sun-vector knowledge is 27° (95th percentile): ADCS-P002 and the ±5° of C-22 are not met, while generation falls only 2 % (4.56 against 4.65 W). The pointing requirement exists for power, so it is restated as what the power budget needs: sunlit-averaged generation loss from pointing ≤ 5 % and the Sun within 30° of +Y for ≥ 95 % of sunlit time, both in every Monte Carlo trial with the photodiode-and-albedo model; sun-vector knowledge is not a requirement (C-22's ±5° is withdrawn). The power budget carries the albedo-case generation. An albedo-immune +Y sun sensor is the recorded option if the EM photodiode test (TP-ADCS-003) shows worse than the modelP3F-G-07 (GN&C closure)
C-24Residual-dipole limit lowered from 10 to 7 mA·m² (design 3 mA·m²): with the photodiode-and-albedo model ADCS-P002 passes in every trial up to 7 mA·m² (worst 5.0 % loss, 96.3 % within 30°) and fails in 6 of 40 at 10 mA·m² (7.7 %, 84.9 %). The limit is a test criterion on the flight unit (ETP Helmholtz-cage measurement); a unit above it is demagnetised or re-harnessed, or gets the albedo-immune +Y sun sensor (the generic model gives 1.8 % / 99.4 % at 10 mA·m²)P3F-G-07 (C-23 check)

What remains

What closed means (CDR report §7.1)
KindCountWhat remains
Verification items (VI)33 RIDs; 228 items in the generated register (SQSO-VIR-001)Each with a test, a pass criterion, an event and date, and an owner; most fall on the EM (2027-06 to 2027-07) and the protoflight campaign
Decision points (DP)34 RIDs; dated actions DA-01 to DA-22 (SCHEDULE §5)Each with an owner and a date; the PI owns most of them
Chair decisions (CH)35 RIDs; decisions C-1 to C-24 (§4)Proposals by AI reviewers, not decisions of a board: they bind nothing until the PI ratifies them (DA-01, by 2027-01-12)

What the PI must do next

Dated PI actions (CDR report §7.3)
ByAction
2026-11-06Request the NASA DAS usage agreement (DA-06); ISIS AntS RFQ with its ICD (DA-19)
2026-11-15Request the FCC Space Bureau consultation with the agenda (DA-11)
2026-12-01Name the independent PDR board (DA-03); ratify the board firmware languages (DA-22)
2026-12-15Accept or reject the reliability estimates (DA-02, C-9); export counsel (DA-13); engage the layout designers (DA-04); vendor statements V-1, V-2, V-5, V-6 (SQSO-MFG-003 §12)
2026-12-31Name the contracting legal entity (DA-05); send the integrator RFQs (DA-07)
2027-01-05Telecommand station agreements (DA-10)
2027-01-12Ratify or reject chair decisions C-1 to C-24 and CR-2026-007 to -019 (DA-01); the proposed requirement wordings of DA-20; independent PDR
2027-01-15EM order, after the procurement data reviews (DA-18) and the parts' vendor actions
All 22 dated actions with owners and pass criteria (schedule §5)
Decision points and dated actions (integrated master schedule §5)
IDDecision or actionOwnerDuePass criterion or outcomeStatus
DA-01Ratify or reject CR-2026-007 and CR-2026-008 (approved by the review chair only), decide CR-2026-009 to CR-2026-019 (docs/project/CHANGE_REQUEST_LOG.md), and ratify or reject the review chair's decisions C-1 to C-24 (SQSO-REV-CDR-002 §4)PI2027-01-12Each CR's CCB decision reads Approved, Approved with conditions or Rejected, dated and signed by the PI; a rejected change is reverted in the documents it touchedOpen
DA-02Accept or reject the Class D reliability estimates (L1/L2/L3 0.75 / 0.61 / 0.51; 0.86 / 0.71 / 0.59 with the reliability programme) and keep or drop the programme (≥ 500 h EM flatsat, ≥ 200 h FM burn-in)PI2026-12-15Decision recorded in RELIABILITY_ANALYSIS §5 and MISSION_SUCCESS_CRITERIA §8; if the programme is dropped, FLATSAT_500H and FM_BURNIN leave the schedule and the estimates revert to the allocation caseOpen
DA-03Name the independent PDR board: a chair and at least two reviewers outside the team covering systems, electrical and RF, and flight software; invitations with the 2027-01-12 datePI2026-12-01Names, affiliations and conflict-of-interest statements in PROJECT_PLAN §6.2; data package to the board by 2026-12-29Open
DA-04Engage two PCB layout designers (KiCad, IPC-6012 Class 3) for a 2027-01-12 start; decide whether the layout starts at risk on the PDR packagePI2026-12-15Agreements in place for both designers; with one designer the plan has −20 d float (§3)Open
DA-05Contracting legal entity named (DP-1)PI2026-12-31An entity able to sign the launch services agreement, cross-waivers, insurance declarations and export agreementsOpen
DA-06NASA DAS: software usage agreement requested by 2026-11-06 and in hand by 2026-12-15; DAS run on the ODAR Draft D cases by 2027-01-08; ODAR Draft E with the DAS output by 2027-01-12, for the early FCC filing (2027-01-19)Systems engineer2027-01-12DAS reproduces ODAR Draft D: orbital lifetime ≤ 5 years after the end of the 2-year mission at 485 km and 1.85 kg with P ≥ 0.9 under the conservative solar projection, and re-entry casualty risk ≤ 1:10,000 (NASA-STD-8719.14C). If DAS disagrees, the cap moves by CR to the highest altitude DAS passes, before the contract negotiation starts (2027-02-23)Open
DA-07Integrator RFQs to Exolaunch, ISISPACE, SEOPS, D-Orbit and Maverick, each asking for: the mission ICD at the contract; the attenuated EXOpod Nova shock MPE at the CubeSat interface; the dispenser thermal analysis for the assigned flight and slot with the deployment time; the SSCMAN 91-710 and battery failure-tolerance requirements; the coupled-loads approachPI2026-12-31Five RFQs sent with these items; replies logged in docs/ORBITAL_ACCESS.mdOpen
DA-08Integrator data with the signed contract: mission ICD, levels, attenuated shock MPE, 91-710 and failure-tolerance requirementsPI (contract signatory)2027-06-30ICD received; LVR and ETP levels replaced by CR; VI-07 (shock) and EPS-23 (failure tolerance) assessed by 2027-07-14Open
DA-09IARU coordination: request on 2027-01-26 after the early FCC filing; letterLicensee (KK6GDB)2027-05-18Coordinated downlink and uplink frequencies frozen in BASELINE §7 by CR; with no letter by 2027-05-18 the licensee asks the IARU Satellite Advisor for status and the contract proceeds on the requested windowsOpen
DA-10Telecommand stations: written agreements with at least two stations at least 1,000 km apart, each able to command aloneLicensee (KK6GDB)2027-01-05Agreements signed; stations named in the early FCC filing and the IARU request; VI-GND-02 site survey of eachOpen
DA-11FCC Space Bureau consultation (D3): requested by 2026-11-15 with the agenda (docs/regulatory/REGULATORY_ROADMAP.md Rev D §6): the ITU API path and timing (REG-05), whether an early failure ends the mission (ODA-05), the contact timeouts N and M, and the beacon kept with a failed receiver (REG-11); meeting by 2027-01-05Licensee (KK6GDB)2027-01-08Outcome recorded by 2027-01-08, before the early filing (2027-01-19). ODA-05 fallback: if an early failure counts as the end of the mission, the 460–465 km band of BASELINE §3 is adopted by CR before the contract negotiationOpen
DA-12Dispenser soak (THM-06, THM-07): the integrator's dispenser thermal analysis for the assigned flight and slot, with the deployment time, requested in the RFQ (DA-07) and delivered at the contractPI (licensee) with the integrator2027-06-30Pack ≤ +50 °C and ≥ −15 °C at deployment, boards within their non-operating limits (V-THM-5). Fallback if the hot result exceeds +50 °C, in order: a deployment-time limit in the contract from the integrator's transient; a low-absorptance finish on the pack-facing surfaces (THERMAL_ANALYSIS §6.5); integrator pad conditioning (purge or air conditioning until fairing close); if none brings the pack to ≤ +50 °C, the PI decides between a lower storage SOC and the NRCSD backupOpen
DA-13Export counsel engaged; export memo Rev B (authentication versus encryption; foreign integrators)PI2026-12-15Counsel's written opinion; TAA need decided before the contract negotiation (2027-02-23)Open
DA-14Panel vendor RFQ with the body-panel cells offset 1 mm from the hinge edge (wing sweep, MECHANICAL_DESIGN §6.6)Mechanical lead2026-12-31RFQ states the offset; the vendor confirms before the panel order (2027-01-15) that the 45° sweep clearance is ≥ 0.35 mm with its tolerancesOpen
DA-15Venting analysis of every enclosed volume from the CAD (VI-LV-12): the gross 1U volume, the battery clamp cavity, the pocket behind the heat spreader; the RF shield cans are done (V/A 3.2–9.4 m, SQSO-RF-BRD-001 D)Mechanical lead2026-12-15Each volume / vent area ≤ 50.8 m (CDS §2.1.9); required holes on the drawings in the PDR packageOpen
DA-16SWE-220: measure the cyclomatic complexity of the safety-critical Rust files with a tool and gate it in CI, or tailor by CRFlight software lead2026-12-15Every function in the safety-critical components (SDP §3.2) ≤ 15, or a CR listing each exception with its justification; result in docs/software/NPR7150_COMPLIANCE_MATRIX.md item C-4Open
DA-17Flexible 2 m AntS tapes in the ADCS Monte Carlo (ADCS_DESIGN §11.5): element mass, stiffness and damping from the ISIS ICD (with AV-V7); flexible-appendage case; EM measurement of the deployed tape's first mode and damping in the EM testsADCS and flight software lead2027-02-26 (analysis); EM measurement before the CDR (2027-09-28)With the tape's first mode and a damping ratio no higher than the measured or 0.5 %, the spin about +Y converges and +Y stays within 15° of the Sun for ≥ 90 % of sunlit time; the measured first mode within ± 20 % of the model's, or the Monte Carlo re-run with itOpen
DA-18Procurement data reviews before the EM order: V-HAR-3 (vendor drawings, gold part numbers), V-HAR-11 (ASTM E595 per part number), EPSB-09 (FM12 interrupting rating against the 209 A prospective short, 60 °C rerating, termination code; SMF24A leakage), JETB-07 (every carrier BOM line on the manufacturer's data sheet)EPS designer, harness designer, payload lead2027-01-15Each data sheet or drawing cited in the BOM "MPN check" column; FM12 interrupting rating ≥ 209 A at ≥ 16.8 VDC and ≥ 5 A at +60 °C; storage drain with the SMF24A's +60 °C leakage ≤ 20 µA; every item without E595 data coded A–E or tested; a failing part changed before the orderOpen
DA-19Drawings before the layout: VI-RFB-12 (AntS RF port, coax plating, attenuation, inner conductor; by 2026-11-13, RF lead; ISIS AntS RFQ with the ICD by 2026-11-06); JETB-06 (NVIDIA DG-10931-001 and TDG-11127-001 through a developer account); JETB-12 (Molex drawings)RF designer; payload lead2027-02-01VI-RFB-12 pass before the RF layout (2027-02-16); V-JET-2 passes before the carrier layout (2027-03-16); J1 mated height ≤ 13.2 mm and J2 ≤ 7.7 mm from the drawings, else the right-angle J1 fallbackOpen
DA-20Ratify the proposed wordings TBR-MRD-002 to -005 and TBR-SYS-002 to -004PI2027-01-12Each TBR closed in its document (ratified, amended or rejected)Open
DA-21Shock (VV-07): decide VI-07 from the integrator's attenuated shock MPETest lead2027-07-14Analysis passes only if the vibration-equivalent SRS (24 / 53 / 85 / 60 g at 100 / 500 / 1000 / 2000 Hz) envelops the MPE below 2000 Hz; otherwise an EM shock test at MPE + 3 dB, 2 actuations per axis, in the EM tests (costed in software/simulation/cdr/pm/test_cost.py)Open
DA-22Ratify the board firmware languages: RF board TNC in Rust no_std with the OBC's pinned toolchain (proposed, SQSO-SRS-TNC-001 §7); EPS controller in C11 to MISRA C:2012 with TI MSP430-GCC (recommended, SQSO-SRS-EPSC-001 §7)PI2026-12-01Decision recorded in SMART-QSO-SDP-001 §3.4 and each specification's §7 before the firmware designs go into the PDR package; if Rust is chosen for the EPS controller, a CR with the nightly toolchain and its qualification plan (CR-2026-004 covers only the pinned stable toolchain)Open

Risks the review accepts

The documents

Every design value is governed by the baseline; where another document disagrees, the baseline is right. SQSO-BL-001 §0